Click to download ESMP_mandatorily_annexed_to_the_Financing_Agreement
Template of the ESMP mandatorily annexed to the Financing Agreement (FA)
General considerations
Federal Ministry of Transportation is planning to implement the Kano-Maradi Railway Project (the
Project). The Bank has agreed to provide financing, implementation support and monitoring for
the Project.
Federal Ministry of Transportation will implement measures and actions of this Environmental and
Social Management Plan1 (ESMP) so that the Project meets all the requirements of the Bank
Environmental and Social Operational Safeguards (OS) and the National policy and legal
requirements.
Where the ESMP refers to specific plans, whether they have already been prepared or are to be
developed, the ESMP requires compliance with all mandatory provisions of such plans.
The table below summarizes the material measures and actions that are required, the basis of the
requirement, the timing of the measure or action, and the criteria to be used for determining whether
the required measure or action has been successfully achieved. Federal Ministry of Transportation
is responsible for compliance with all requirements of the ESMP even when implementation of
specific measures and actions is conducted by an entity different from the Project Implementation
Unit (PIU).
Implementation of the material measures and actions set out in this ESMP will be monitored and
reported to the Bank by Federal Ministry of Transportation as required by the ESMP and the
conditions of the legal agreement, and the Bank will monitor and assess progress and completion
of the measures and actions throughout implementation of the Project.
As agreed by the Bank and Federal Ministry of Transportation, this ESMP may be revised from
time to time during Project implementation, to reflect adaptive risk management of project changes
and unforeseen circumstances or in response to assessment of project performance conducted under
the ESMP itself. In such circumstances, Federal Ministry of Transportation will propose and agree
changes with the Bank, and then update the ESMP to reflect such change